Work will include, but not limited to, the installation of approximately 3,000 feet of 8 inch HDPE water main by directional drill along Voorheesville Ave, Center Street and Pleasant Street, including re-establishing water service to 48 properties. Work will include associated restoration including road paving. It is proposed for site work to commence no later than Nov 30 with substantial and final completion before June 2024.
Drawings and Specifications are available on the Village website however; only contract documents obtained from C.T. Male Associates, 50 Century Hill Dr, Latham, NY 12110 will enable a prospective bidder to be identified as an official plan holder of record. You can email Anne-Marie Mull at a.mull@ctmale.com (or call 518-786-7400) to obtain official documents and be registered as an official plan holder.
'Unofficial' bid document links are also available below--